SRA serves to facilitate the rehabilitation of slum dwellers in authorised dwelling units
 Need For Slum Rehabilitation
          + History
 Salient Features
 Constitution and Functions
          + Responsibilities
          + SRA as a Planning Authority
          + Jurisdiction
 Rehabilitation Schemes
 Scheme Submission and Approval
          + Flowchart of Stages
          + Description of Stages
 Map of Mumbai
 Dharavi Upcoming
 Feed Back
 Contact us

 

HOME

  Projects

  Important
  Notifications

        + Notifications
      + Tender Notices
      + News
      + Photos

  Appeal Cases

Second Stage

 

1. Initial scrutiny of the proposal is carried out by the concerned sub-engineer. It is ensured that all requisite documents are submitted along with the proposal.

2. If the proposal is in order, the amount of scrutiny fee to be paid is worked out by the sub-engineer.

3. The scrutiny is paid by the developer.

4. Annexure II is forwarded to the competent authority for certification.

5. Annexure III is simultaneously forwarded to the financial wing for scrutiny.

6. Annexure I is scrutinized by the engineering wing.

7. After Annexure II & III are certified by the competent authorities, approvals to LOI, layout. Intimation of Approval and commencement certificate to the first building for work upto plinth are processed. Endeavor is made to issue all these four approvals at one go, at-least for the first rehabilitation building.