Second Stage
1. Initial scrutiny of the proposal is carried out by the concerned
sub-engineer. It is ensured that all requisite documents are submitted along
with the proposal.
2. If the proposal
is in order, the amount of scrutiny fee to be paid is worked out by the
sub-engineer.
3.
The scrutiny is paid by the developer.
4. Annexure II is
forwarded to the competent authority for certification.
5. Annexure III is
simultaneously forwarded to the financial wing for scrutiny.
6. Annexure I is
scrutinized by the engineering wing.
7. After Annexure II
& III are certified by the competent authorities, approvals to LOI, layout.
Intimation of Approval and commencement certificate to the first building for
work upto plinth are processed. Endeavor is made to issue all these four
approvals at one go, at-least for the first rehabilitation building.