Fourth Stage
1. Plans for the further buildings both for sale and rehabilitation
are then approved.
2. Building permissions for
the sale buildings are given in the proportion of the permissions given to the
rehabilitation buildings.
3. Upon completion of
rehabilitation building/ wing, list of allotment is drawn up. The allotment is
done in the joint name of the head of the household and the
spouse.
4. Building completion certificate is submitted by the
architect.
5. After checking of the building and compliance of the IOA
conditions Occupation permission to the building is granted. The slum dwellers
as per the allotment list are given possession of the
tenements.
6.
SRA issues identity cards to the slum
dwellers.
Fifth Stage
1. Further construction of
the remaining building/s is then taken up.
2. Further building
permissions as well as occupation permissions to the buildings is then granted
in due course.
3.
Upon completion of the last buildings in the layout, the
underlying land is transferred on lease to the society of slum dwellers. In case
of Government lands, the lease rent is nominal.
4. Separate property cards
for the rehabilitation building plot and the sale building plot as well as for
the reservation plots to be handed over are prepared. SRA acts as facilitating
agency in case of any difficulty with the revenue
authorities.