* News*

SLUM REHABILITATION AUTHORITY

      Twin Towers war hots up        

Hemal Ashar

 JULY 21, 2004

      

The three-man committee from the Indian Institute of Technology (IIT), investigating the stability of Cumballa Hill after a portion was excavated for the construction of the Sale Towers (Twin Towers), is set to file a final report any time now.

S D Corp, the developer and a sister concern of the giant Shapoorji Pallonji group has been embroiled in an acrimonious legal battle with the Carmichael Road Citizens’ Committee (CCC) over the construction of two 60-floor towers.

While the committee commissioned independent studies regarding hill safety, S D Corp commissioned two independent studies that claim that Cumballa Hill has not been destabilised because of the construction, but in fact strengthened by it.

A senior S D Corp official, said that the CCC studies lacked authenticity as the committee’s so-called experts, “had not visited the site, basing their reports on hearsay and conjecture.” 

S D Corp also said that, “The opposition is the reason for the delay by the IIT committee in submitting a report. (The committee has taken 15 months to  submit an interim report.) They have placed hurdles throughout the process.”

S D Corp especially singled out foundation engineer V C Deshpande, whose report says, “rectify the serious deficiencies urgently — lest the fragile stability of the cliff amplifies into a mishap of biblical proportions” as a  “person who is not qualified to comment as he is only an engineer and not a geotechnical expert.”

Deshpande hit back with, “I have based my interpretations on the IIT committee’s interim report.  I have also personally visited the site. If I am unqualified to comment then why am I on the Bureau of Indian Standards (BIS)?” he asks.

With the opposition and the developer in combat mode, the decibel levels are set to go up in what has been one of the most controversial construction projects in Mumbai.

Tower facts

According to S D Corp: Two towers are coming up with a three-level lobby, nine levels of parking and 49 living floors. The total is 60 floors. The first tower is to be finished by the end of 2005.

Tower 1 construction has reached the 17th floor.  We have reached the 10th level in Tower II.  A third tower will also be constructed, the company states.

Reports

Richard E Goodman,  Globus Engineering Inc, California:‘‘The treated slopes above the excavation are judged to be stable The rock mass at the top of the slope has been strengthened by  block-pinning and dental work and it poses less risk to structures above or below than it had before the construction operations.”

R J Chandler:“I do not agree that the slope is geologically unstable.  The stability of the slope will improve further when the  back-filling against the slope is complete at the end of construction.”