Third Stage
1. The society draws lots for
allotment of the tenements to the members who are ready to participate in the
scheme. Draw for the non- participating members from the remaining tenements is
also drawn.
2. The developer arranges for transit accommodation to the slum
dwellers, which can be either on-site or off site, as mutually agreed between
the slum dwellers and the developers.
3. In case the developer has
difficulty in arranging for suitable transit accommodation, due to site
constraints, SRA extends all help to the developers to locate suitable site in
the vicinity for construction of transit camps and helps to obtain permissions
from concerned authorities for the same. In case no suitable site is available
in the vicinity, transit camps of MHADA, MMRDA, etc can be taken on rental basis
by the developers.SRA extends all possible help for obtaining these transit
tenements from these authorities.
4. Draw of lots for allotment
of transit tenements is drawn.
5. The slum dwellers are
shifted to the transit camps and their hutments demolished. The slum dwellers
who do not agree to participate in the scheme are given notice by the society
staling the allotment details and requesting them to participate in the
scheme.
6. If these members do not agree to participate within 15 days of the
approval of the proposal, they are physically evicted from the site under the
provisions of Sec 33 & 38 of Maharashtra Slum Areas (Improvement, Clearance
and Redevelopment) Act, 1971, to ensure that there is no obstruction to the
scheme.
7. After demolition of the structures, work upto plinth is
completed.
8.
After checking the plinth dimensions, further permission to
carry out construction beyond plinth is granted.